The main electric supply station/substation is
the installation/utility interface point where further
transmission, distribution and utilization of
electrical power, the monitoring and control of such
power or equipment and the protection of
electrical equipment or systems becomes the sole responsibility
of the Government. Electrical power will be supplied
by the same utility over one or more
incoming power lines that are metered by the
use of items of equipment provided and maintained by
the utility. The design of new stations, or
modifications to existing stations, must be coordinated
with the supplying utility and with any other suppliers
or users of power supplied through the station. Such coordination should be
accomplished by the responsible field operating agency, or a designer employed
to accomplish the coordination and design of new electrical facilities.
Complete coordination should be performed to ensure proper protection for electrical
equipment and systems, to obtain the required degree of availability,
reliability and maintainability, and to achieve the most cost effective
billing, construction, operation and
maintenance costs during a station life of 25
years or less.
a. Billing.
Since electric utility rates and rate structures
vary from state to state and with the user’s energy and demand requirements,
the serving utility will be contacted at an early point in the planning process
to assist in determining probable electric rates and charges. In dealing with a
large user, the serving utility often has
flexibility to negotiate a special rate. Where
the new installation will be large, this aspect of utility charges will be
vigorously pursued. A typical facility monthly electric bill will contain the
following types of charges:
(1) Energy charge based upon
kilowatt-hours (kWH) used. The energy charge may be based on time-of-day usage
(the “on-peak” rate often being higher during the 12 daytime hours of the
normal five day work week than during the “off-peak” remaining time).
Additionally, many utilities charge more for energy used during the
“peakseason” summer months than for energy used during the “off-peak-season”
fall, winter, and spring months.
(2) Demand charge based upon
the maximum kilowatts (kW) used. This charge is based on the maximum rate at
which energy is used (kW demand) for a period of 15, 30, or 60 consecutive minutes
(depending on the utility) during “onpeak” hours. Alternately, demand charges
may be based partially on “on-peak” demand and partially on “off-peak” demand.
(3) Power factor charge.
This
charge may be based upon the facility power factor recorded during the maximum
demand period or upon total kWH and
total kilovar-hours (kVARH). Often the power factor adjustment is a multiplication factor
applied
to the kWH and/or the kW demand. Some utilities will charge a penalty for low
power factor (below the 0.85 to 0.90
range) and offer a credit for a high power factor.
(4) Fuel adjustment charge. This charge is a surcharge
or a credit to the energy charge and is based upon the price paid by the
utility for fuel for its generating stations.
(5) Facility charge. This is a fixed
monthly charge which is based upon the sophistication of
the utility’s revenue metering equipment,
ownership (utility or user) of the main supply station(s), and number of points
metered.
b. Revenue metering
A utility provides a totalizing watthour meter
equipped with a demand register that is supplied by highly accurate instrument transformers.
A demand type of varhour meter will be provided by the utility when the rate schedule
includes a power factor charge. Utility meters cannot be used for any other
purpose without prior approval by the utility. Revenue metering equipment will
be provided by the Government only when required by the utility, and will
comply with the utility requirements.
c. Energy conservation requirements.
Reduction in energy usage is a national goal.
Several programs have been implemented to effect energy
reduction, including utility monitoring and
control systems (UMCS). Provide for future UMCS monitoring by installing the
following equipment during substation construction: potential and current transformers,
watt and VAR transducers, circuit breakers with auxiliary contacts, and
watt-hour meters with pulse initiators for interface to UMCS equipment. See TM
5-815-2 for additional information.
d. Power factor correction.
Provisions
for future installation of shunt capacitor equipment will not be
initially provided in the main electric supply station. Power factor
correction capacitors should be provided at or near the terminals of
inductive devices to minimize energy losses in the electrical supply
systems.
e. Protection.
The
ratings and settings of overcurrent protective devices will be selected to
afford optimum protection of the electrical equipment and systems. Utilities
will have additional requirements when any electric power generating units on
the site are to be paralleled with the utility. The utility may also have
special requirements for
protection and coordination of its system on a
nonparalleled installation. Some utilities have carrier relaying schemes, and
may require the Government to provide line relays, or companion type relays,
power supplies and housing for carrier relaying equipment. Auxiliary equipment
such as batteries and chargers, annunciator panels, and supervisory or telemetering
equipment may need to be provided or housed or supplied. Written utility
requirements and approval of the system proposed will be obtained in the
criteria development or early design stages of a project.
f. Short-circuit capacity.
The available shortcircuit capacity of the
electrical power sources influences the design of circuit-controlling and protective
devices located in the station, and those provided in the distribution system.
The serving
utility’s future planned short-circuit current
should be considered in the design as well as the short-circuit current available
at the time of design.
g. Coordination study.
A
short-circuit study and a protective devices coordination study will be performed
for each new or modified station or substation. The studies will be performed
at a date early enough to ensure that proper equipment can
be specified and proper protection provided.
Refer to IEEE Std 242 and TM 5-811-14 for guidance regarding coordinated power
system protection. A short-circuit and protective devices coordination study
will be prepared to be used as a basis for equipment ratings and protective
devices settings, and, for large projects, will include settings for 20, 40,
60, 80, and 100 percent load using typical devices.
No comments:
Write comments